Road Construction Update for Sept. 29,2012

Both of the east Capitol Dr. ramps will reopen on Monday morning. The contractor is planning to finish prepping the gravel north of Capitol Dr. Monday and then place roadway concrete south of Capitol Dr. on Tuesday and Wednesday. If they can get their equipment and crews ready they will also try to work on driveways and sidewalk north of Capitol Drive. We are getting closer to completing the project and everyone should see some more progress in the next couple of weeks.
Thanks,
Description: Description: exp_Logo_cmyk.png
The new identity ofTeng & Associates, Inc.

Casey Wierzchowski, P.E.
Senior Project Engineer
expUS Services Inc.